DSK’s project has been implemented in two phases. The first phase directly supported 10,000 beneficiary households (BHHs) for 3 years. Upon completion of the first phase in early 2012, DSK is currently directly supporting an additional new batch of 15,000 BHHs for another 3 years. Phase 1 BHHs will continue to be monitored and supported by DSK on a needs-basis, and all eligible households from Phase 1 and Phase 2 will benefit from the Nutrition Component addition.
Phase 1
Start Date: 1 April 2009
End Date: 31 March 2012
Phase 2
Start Date: 1 April 2012
End Date: 31 December 2015
Project Area
Dhaka urban slums situated at Kamrangirchar and Korail
See the project areas on Google Maps
Target
10,000 Beneficiary Households (BHH) Phase 1
15,000 Beneficiary Households (BHH) Phase 2
Total = 25,000 BHHs
Years to Graduate
2 years
Budget & Cost per BHH (for Phase 2)
Total livelihoods budget is BDT 340,745,388
cost per BHH is BDT 22,716
of which the direct delivery per BHH is BDT 15,712
Total nutrition budget is BDT 53,491,878
cost per BHH is BDT 2,140
of which the direct delivery per BHH is BDT 1,925
Background of DSK-SHIREE Project
DSK has been working for last 20 years with slum dwellers in Dhaka and Chittagong to improve their living standards through health services, WatSan facilities and improved access to income generating activities for a long time. Their experience in doing this has meant that they are able to implement a scale fund project in two urban slums in Dhaka with the name of “Moving from extreme poverty through the economic empowerment of extreme poor households” since April 2009.
Extreme poor people have migrated to urban areas due to riverbank erosion, natural disasters and a lack of employment. They are contributing to national GDP through working in the informal and formal economy. However, the issue of urban extreme poverty:
Considering the context and growing concern for urban extreme poverty, DSK has initiated this project with the financial assistance of shiree.
Key Aspects
Outputs
See the works of SHIREE funded project of DSK Bangladesh on flickr
The Japanese federal government modified up its fundamental financial evaluation in a regular monthly record…
Round 1 of the Scale Fund was designed to cover a broad spectrum of issues facing…
Round 4 of the Innovation fund focused on achieving sustainable impacts in the lives of…
Round 3 of the Innovation fund targeted marginalised sub-sectors of the extreme poor who have…
Round 2 of the Innovation Fund was designed to target those geographical areas which suffer…
Round 1 of the Innovation Fund explicitly funded projects that focused on eradicating extreme poverty…